Maintenance Zone (August 8, 2019)

    Dia de Wijs
    • Public
    Asked by Dia de Wijs 122 days ago Answers (1)

    The two export cables for the Hollandse Kust (west) Alpha platform are crossing the Hollandse Kust (noord) Wind Farm Zone. It seems that the maintenance zone for these cables is less than 500 metres. Is that correct?

    1 answer

      • Dia de Wijs
        • Public

        Dia de Wijs 122 days ago

        That is correct. TenneT decided to reduce the spacing between the cables to 200 metres. The spacing between the TenneT cable and the telecom cable remains 500 metres, hence the total zone between the two parcels is 500+200+500+500= 1,700 metres.