The Wind Farm Site Boundaries are not always exactly 500 metres from a cable, does this have any impact?
The boundaries of the Wind Farm Sites as published in the Wind Farm Site Decisions are binding. For telecom cables a maintenance zone of 1,000 metres applies. In some cases the telecom cables and pipelines are not exactly in the middle of this maintenance zone due to small bends.