  • Regulations during construction of the offshore wind farm (May 15, 2017)

Regulations during construction of the offshore wind farm (May 15, 2017)

    WOZ_RVO.nl
    • Public
    Asked by WOZ_RVO.nl 158 days ago Answers (1)

    These questions concern the regulations during the construction of the offshore wind farm:

    1. Is a guard vessel to secure the construction site and passing traffic mandatory?
    2. With reference to the Water Decree, art. 6.16h: Who is responsible for identification marks and beacons of the construction site?
    3. Who pays for guard vessel(s), identification marks and beacons?

    1 answer

      • WOZ_RVO.nl
        • Public

        WOZ_RVO.nl 158 days ago
        1. During construction activities guard vessel(s) are mandatory, at least one, in many cases two. This is subject to approval by the Netherlands Coastguard.
        2. The site developer is responsible for the identification marks and beacons of the construction site.
        3. The costs for guard vessel(s), identification marks, beacons and the mandatory Notice to Mariners are at the expense of the site developer.