    Please clarify if positioning of construction vessels (including jack-ups and anchors) during site construction outside the HKZWFS boundary lines is allowed?

    1 answer

      • WOZ_RVO.nl
        • Public

        WOZ_RVO.nl 197 days ago

        This is allowed if positioning (jack-up and anchoring) is done in open sea. Positioning in maintenance zones or safety zones of existing cables and/or pipes and/or installations is prohibited unless agreed upon otherwise in a proximity agreement with the owner.