Offshore wind requirements/ trenching (25-02-2016)

    WOZ_RVO.nl
    • Public
    Asked by WOZ_RVO.nl 539 days ago Answers (1)

    My question relates to the Borssele Offshore wind requirements. Can you please confirm that trenching of in-field cables are not required.

    1 answer

      • WOZ_RVO.nl
        • Public

        WOZ_RVO.nl 539 days ago

        There are no requirements for the burial of in-field cables in the Wind Farm Decisions. Trenching is not mandatory.